Schedule for Phase 1

Note: All dates below are for 2006.

For a more detailed version of Phase 1 Milestones, please see the Phase 1 Task Spreadsheet

Tentative Phase 1 Schedule:

Dates Activity
6/15-7/17 Investigation/Design
6/15-9/3 Implementation
9/4-9/10 Test server implementation
9/11-10/1 QA and Usability testing
10/2 Pilot server up and running
Date Implementation Milestones
8/14 OSID Mock-up completed (Gaurav and Steve)
8/17 Create a citation and put it in Citation List (Jim)
8/25 Populate Citation List from mock search results (Jim)
9/3 OSID implementations return search results to UI (Gaurav, Steve and Jim)
9/10 Server can be run for QA and Usability testing

See also Vacation and Travel Schedules.